| Project Name |
Project Number |
Bid Date |
Award to: |
| Ground Transportation Center Renovation |
TRE001-20 |
6/20/13 |
Woodruff Construction |
| Five Seasons Parkade Skywalk Phase I Interior Renovations |
635125-01 |
3/6/13 |
Olmstead Construction |
| 2nd St SE Parking Ramp @ 7th St - General Construction |
635120-20 |
1/9/13 |
Knutson Construction Serv Midwest, Inc. |
| 2nd St SE Parking Ramp @7th St - Mechanical |
635120-21 |
1/9/13 |
Bowker Mechanical Contractors LLC |
| 2nd St SE Parking Ramp @ 7th St - Electrical |
635120-22 |
1/9/13 |
Justice Electric Co. |
| Veterans Memorial Phase III Package |
VME001-06 |
12/19/12 |
Bid Package: #2 & 4 - Tricon #3 - Seedorff #6 - Pearson Wall #7 - Grazzini Bros #8 - J Wood Sports #11 - Blackhawk #12 - Day Mech. #13 - Hawkeye Elec. |
| CR Animal Care & Control Building |
PDE001-20 |
9/26/12 |
Portzen Construction |
| CR City Services Center Bid Pkg 2 - Phase 2 Demo, Sitework & New Building (General Contractor) |
PWE006-21 |
9/19/12 |
Miron Construction |
| CR City Services Center Bid Pkg 2 - Phase 2 Demo, Sitework & New Building (Demo & Abatement) |
PWE006-22 |
9/19/12 |
DW Zinser Co. |
| CR City Services Center Bid Pkg 2 - Phase 2 Demo, Sitework & New Building (Mechanical & Plumbing) |
PWE006-23 |
9/19/12 |
Modern Piping, Inc. |
| CR City Services Center Bid Pkg 2 - Phase 2 Demo, Sitework & New Building (Electrical) |
PWE006-24 |
9/19/12 |
Acme Electric Co., Inc. |
| CR Convention Complex Audio Technology |
535100-05 |
9/5/12 |
AP Sound, Inc. d/b/a All Pro Sound |
| CR Convention Complex Video Technology |
535100-06 |
9/5/12 |
TS Sports |
| Cedar Rapids Fire Station No. 3 |
308141-20 |
9/12/12 |
Garling Construction, Inc. |
| CR Public Library - West Side Branch |
701057-01 |
9/5/12 |
Garling Construction |
| Veterans Memorial Phase III Pkg |
VME001-06 |
8/15/12 |
Bids were rejected |
| City Services Center Bid Pkg 1 Abatement & Demolition |
PWE006-20 |
7/25/12 |
DW Zinser Co. |
| CR Convention Complex Hotel - Interiors & Exterior Cladding (General Contract) |
535101-08 |
7/11/12 |
Kleiman Construction Inc. |
| CR Convention Complex Hotel - Interiors & Exterior Cladding (Mechanical Contract) |
535101-09 |
7/11/12 |
Day Mechanical Systems, Inc. |
| CR Convention Complex Hotel - Interiors & Exterior Cladding (Electrical Contract) |
535101-10 |
7/11/12 |
Nelson Electric Company |
| Cedar Rapids Central Fire Station |
FDE010-21 |
6/20/12 |
Miron Construction Co., Inc. |
| 1st St SW Outdoor Amphitheater & Festival Grounds |
307218-06 |
6/19/12 |
Knutson Construction |
| CR Transit Bus Garage |
TRE003-20 |
5/16/12 |
Kleiman Construction, Inc. |
| Cedar Rapids Convention Complex Parking Ramp & Skywalk |
535103-20 |
5/2/12 |
Knutson Construction Serv Midwest |