| BID DATE |
CIP# |
TITLE |
DESCRIPTION |
SCHEDULE |
EST BUDGET |
Contact
Person |
12/3/09
bids 11:00 a.m. at Office of City Clerk
Plans currently available at Public Works Dept |
655999-02 |
FY 09 Cedar Rapids Sanitary Sewer Improvements Phase 1 - Lining and
Point Repairs |
13,700 LF cured-in-place lining (8" - 28")
85 LF point repairs |
Early Start Date: 1/18/2010
Late Start Date: 3/15/2010 |
$500,000 |
Dave Wallace |
12/3/09
bids 11:00 a.m. at Office of City Clerk
Plans currently available at Public Works Dept |
301249-03 |
C Ave NE - From Huntington Ridge Rd NE to E Main St NE PCC Pavement, HMA
Resurfacing, and Traffic Signal Improvement Project |
9,500 CY of unclassified excavation; 1,800 LF of various sized RCP storm
sewer; 1,200 LF of 6" subdrain; 14 EA storm sewer intakes; 8,800 SY of
9" PCC pavement; 1,400 SY of 4" PCC sidewalk; 1,700 TON of HMA, Traffic
Signal Installation |
Early Start Date:
4/5/10
Late Start Date:
5/3/10 |
$1,200,000 |
Gary Petersen |
|
12/3/09 Bids 11:00 a.m. at Office of City Clerk
Plans currently available at Public Works Dept
|
TRE013-20 |
GTC Montessori School Flood Reconstruction |
Lump sum contract - remodeling work (including mechanical, electrical,
and plumbing systems, interior finishes and glazing enclosure) to repair
and update 18,790 SF one-story facility (with mezzanine) as a result of
the flood of June 2008. |
Late Start Date: 1/29/10
Completion Date: 5/31/10 |
$2,000,000 |
Loren Snell |
12/8/09
Request for Quotes due 11:00 a.m. at Public Works Dept
Plans currently available |
304224-01 |
Cottage Grove Parkway SE (4232 and 4240) Sluice Gate Installation |
Installation of a sluice gate and structure and removal and replacing of
an intake in the rear yards between 4232 and 4240 Cottage Grove Parkway
SE.
1 EA sluice gate and manhole structure; 1 EA ditch intake |
Early Start Date: 1/18/10
Late Start Date: 2/15/10
Completion Date: 4/16/10 |
Request for Quotation |
Mike Dufoe |
12/10/09
bids 11:00 a.m. at Office of City Clerk
plans currently available at Public Works Department |
301855-02 |
1st Avenue East, from 17th Street SE to Cottage Grove Avenue SE,
Pavement Rehabilitation and Sanitary Sewer Replacement Project |
22,400 SY Milling of ACC Pavement; 221 LF 8" Sanitary Sewer Gravity
Main, Open-Cut; 2,503 LF 8" Sanitary Sewer Gravity Main, Directional
Drilling; 35 Sanitary Sewer Service Reconnections, Open-Cut &
Directional Drilling; 14 EA 48" Sanitary Sewer Manholes; 5 EA Storm
Sewer Intakes; 2,654 SY of Full-Depth PCC Pavement Repair; 655 LF PCC
Curb Repair; 480 SY Partial Depth HMA Patching; 4,665 TON HMA Overlay;
130 STA Pavement Parkings, Polymer Tape; Traffic Signal Modifications;
Misc Water Main Construction |
Early Start Date: 5/17/10
Late Start Date: 6/1/10
60 Working Days |
$1,525,000 |
Lee Tippe |
|
12/15/09
Request for Quotes due 10:00 a.m. at Public Works Dept
|
304990-03 |
Bowman Woods near Chelsea Dr NE Drainage Repairs |
65 CY excavation; 1,200 SF transition mat; 2,100 SF wood excelsior mat |
Early Start Date:
3/22/10
Late Start Date:
4/5/10 |
Request for Quote |
Mike Dufoe |
|
12/17/09 Bids 11:00 a.m. at Office of City Clerk
Plans not yet available |
304116-02 |
17th St SE from 7th Ave to Mt. Vernon Rd Storm Sewer Extension and 17th
St SE South of 8th Ave SE Water Main Extension |
625 SY removal of existing pavements, driveways, curb & gutter; 200 SF
removal of existing sidewalk; 535 LF storm sewer main, 15" RCP; 364 LF
storm sewer main, 18" RCP; 2 ea. storm sewer manhole, 48"; 5 ea storm
sewer intake, Metro RA-3; 3 ea storm sewer intake, RA-41 (IDOT); 1 ea
storm sewer intake extension unit, RA-42 (IDOT); 274 LF watermain, 6"
DIP; 1 ea install fire hydrant; 530 SY PCC pavement, non-reinforced, 7",
Class C; 65 SY PCC driveway, 5"; 30 SY PCC sidewalk, 4"; 175 SY PCC
sidewalk ramp; 25 SY asphalt cement concrete driveway, 5"; 520 SY
asphalt cement concrete overlay, 2" surface, PG 58-28 |
Early Start Date:
3/22/10
Late Start Date:
5/4/10 |
$185,000 |
Chris Strecker |
|
12/17/09 Bids 11:00 a.m. at Office of City Clerk
Plans not yet available |
PWE018-20 |
4th Ave SE Parkade Flood Recovery |
Reconstruction of the 4th Ave SE Parkade that was damaged by the flood
of June 2008. Repair of the elevators is being completed under a
separate contract. This project includes architectural, plumbing,
electrical and mechanical renovations and sustainable upgrades. |
Start Date:
1/25/10 |
$1,350,000 |
Sandy Pumphrey |