CR Transit Bus Garage, 427 8th St NW 

Bookmark and Share

Description

  • The CR Transit bus garage and administrative offices were significantly damaged by the Flood of 2008.
  • The new facility will be built on the same site with all critical components raised above the flood level.
  • The new bus garage will be the storage and maintenance facility for 30 full-size buses.
  • The facility will serve as CR Transit’s administrative offices. 

Estimated Timeline

  • July 2012 – Construction begins
  • April 2013 – Construction complete

Funding Sources

  • $3,300,000 in FEMA repair funds
  • $600,000 in Iowa Department of Transportation funds
  • $300,000 in City Capital Improvement Project (CIP) funds
  • $300,000 in Corridor Metropolitan Planning Organization Surface Transportation Program funds

Total Estimated Project Cost: $4.5 million